The warehouse complex at the Wallersdorf site is currently the largest single site for after-sales logistics at a well-known Bavarian automobile manufacturer. Oehler Regeltechnischer Service GmbH supplied the building automation for both construction phases.
Key data of the construction project
Construction period: phase 1: 2015-2016 / phase 2: 2018-2019
Location: Wallersdorf, BY
Size: approx. 380,000 m2
Type: Distribution centre and spare parts warehouse
Our services
- Cost savings in cabling thanks to bus components
- Connection of self-sufficient heating and ventilation systems
- KNX Bus connection
- Control of the heating circuits and ventilation systems
- Operating and fault message management
- Central system operation via building management system
- Central meter monitoring
Control details
DDC brand: Schneider Electric
Building control technology: Schneider Electric EcoStruxure
Number of data points: approx. 1200